Sediments removal
eye/The technical engineering staff of the projects directorate which its sub foundation belongs to ministry of water resources "the directorate still continuous in sediments removal process for the ditches and broachers canals in Khadumya and Meda,an and Abughraib within Baghdad province .
And work plan scheduled were sediment removal for Alsalamyat diches in Khadumya as well as cleaning the sub canal of Rashid Alyussif and doing some sediment remove for the sub canal broaching system .
Also huge mount of sediment been removed as well as unblocking the chokes in the broaching system and the irrigation canals.
And in Abu ghraib the process included cleaning the main broaching systems and also the sub ones as well as cleaning the ditches and the progress included the northern and western main Abu ghraib territories and the total length of the cleansed ditches is about 60.7 kilometer and the target one is 76 kilometer ,and the equipments used were bulldozers .
read: 77 date:2008-07-09